5.1 Introduction
5.1.1 Before land can be determined as contaminated by definition a, significant contaminant linkage, must be identified. Unless all three elements of a contaminant linkage are identified then land is not contaminated (source, pathway, and receptor). It is important to fully understand this concept as it will form the basis for the prioritisation process and future site investigations.
5.1.2 If, for example, an area of land is known to be badly affected with potentially dangerous contaminants, it will not be considered of the highest priority if studies confirm there are no specified receptors within the area of influence. If there are receptors evident, the risk assessment process assesses the likelihood of them coming together at any time. If the chances of this are judged as, significant, and the consequences would likely result in, significant harm, or significant pollution of controlled waters, then a significant contaminant linkage will be said to exist and the land will be determined as contaminated land by definition.
5.1.3 Given the lack of scientific information about many contaminants and the site specific nature of risk, it will be the requirement of the council to assess the risk posed on individual sites and decide whether, in their opinion the risk represents ‘significant possibility of significant harm’ SPOSH (DEFRA, 2008)
5.1.4 In summary, for contaminated land to exist the following are pre-requisites:
- One or more contaminant substances;
- One or more specified receptors;
- At least one plausible pathway between contaminant and receptor, establishing a contaminant linkage;
- A good chance that the contaminant linkage will result in significant harm to one or more specified receptors, or, pollution of controlled waters.
5.1.5 No assessment should be undertaken unless both contaminants and receptors are suspected or confirmed. Where there is doubt the situation will be kept under review.
5.2 Identification of Potentially Contaminated Land
5.2.1 The 1990 Act requires that all land within Portsmouth be considered, but also that the identification of contaminated land be carried out in an ordered, rational and efficient manner, based firmly on the principles of risk assessment. This should commence with the consideration of land within the whole of Portsmouth utilising sources of information from council archives, the Environment Agency and other external organisations on the locations of potential sources of contamination.
5.2.2 Collation of geographical information has been incorporated into the contaminated land Geographical Information System. Prior to starting the risk assessment process the Geographical Information System will be used to store details of all potentially contaminative areas, receptor sites and environmental variables, such geology, hydrology and hydrogeology, which may act as contaminant pathway mechanisms. This information formed the basis of the site prioritisation tool, an in-house Geographical Information System, which was developed for the prioritisation of land. Having prioritised sites for inspection, the database is now stored on a proprietary Geographical Information System 'Geoenviron' and the records relating to the desk study risk assessment process will be stored on this database. The information required from consultants is summarised in Appendix F
5.2.3 Data capture is an ongoing process, but most areas of potentially contaminated land have been added to the database with only additional records being found and added and those created through site investigation data. This level of detail allows better information about true site condition. Any land brought to the council's attention will be considered at that time. If any land with indications of being statutory contaminated land is brought to the council's attention, either on our list or newly identified, it would by virtue of being identified bypass the above prioritisation and be the highest priority for the council to consider for the purposes of this strategy. It is not considered necessary to recreate the above prioritised list for strategic inspection of newly identified sites.
5.3 Investigation of Land
5.3.1 A document, loosely based on a Land Condition Record will be created to record the following information regarding each site investigated:
- Site description,
- Risk assessment,
- Current and historic land-use,
- Interested parties,
- Analyses of results from site investigations,
- Receptor and pathway details,
- Determinations,
- Consultations,
- Notices,
- Appeals, and
- Remediation details.
5.4 Prioritisation process
5.4.1 Potentially contaminated land shall, prior to detailed investigation, be listed and categorised according to a preliminary assessment of risk. This is to ensure all further investigative work relates directly to seriousness of the potential risk and the most pressing problems are identified and quantified first.
5.4.2 The prioritisation process will contribute to the overall aim of the strategy in meeting the legal requirements set out in Part 2a of the Environmental Protection Act 1990 and in the inspection duties of local authorities listed in Section 2 of the Statutory Guidance (2012).
5.4.3 After consideration of several different prioritisation tools, the council created its own system using Geographical Information System based on the method in Contaminated Land Research 6: prioritisation & categorisation procedure for sites which may be contaminated (DOE, 1995).
5.5 The Prioritisation of Sites
5.5.1 With its long history of use and redevelopment of land, the council has been proactive in the management of contaminated land. Portsmouth was proactive before many councils and used national government funding available in the 1990s to assess corporate own land holdings that were on the prioritised list.
5.5.2 Land that is brought to the council's attention because of concerns automatically becomes the highest priority site regardless of the ranking, and will be considered at that time.
5.6 Method of Prioritisation
5.6.1 The prioritisation conducted in the 1990s is described in the council’s 2001 strategy, but this in-house approach has been replaced by a proprietary model 'Geoenviron'. Geoenviron is used to store the records across the city and derive an on-going iterative assessment of priority. It is summarised in Appendix K.
5.7 Summary
5.7.1 The strategy for identification is based on historical mapping of the city to identify areas of land where:
- Previous uses indicate contamination may exist;
- There is no existing pollution control regime in place;
- There are known receptors within the area of influence.
5.7.2 It must be understood that the prioritisation of land at the preliminary assessment stage is made on a limited amount of basic data and information, such as old surveys, maps, geological information. As more knowledge of the site is obtained, these assessments will be revised and their priority category may change. The assessment of a site as priority category ‘a’ does not necessarily infer the existence of a significant risk to one of the specified receptors, but it does identify the need for consideration of the site by the Contaminated Land Team.