14.1 Introduction
14.1.1 The legislation and Statutory Guidance is not prescriptive in terms of how quickly the work on contaminated land needs to be completed. It does, however, require each council to set out within this strategy, what it considers to be appropriate timescales for the inspection of different parts of its area.
14.2 Programme for Inspection
14.2.1 Since the publication of the council's contaminated land inspection strategy in 1991 and 2001 the council continues to discharge its statutory duties under Part 2a of the 1990 Environmental Protection Act:
- Identified potentially contaminated land within Portsmouth;
- Prioritised potentially contaminated land for inspection
- Brought about the remediation of land that may otherwise have been statutory Contaminated Land
14.2.2 In Portsmouth, the highest priority sites with an emphasis on sites owned by the council were considered in the 1990s, but professional knowledge will be used to revisit and continue the process.
14.2.3 For each newly identified site that is being considered under our duties, a preliminary conceptual model will be constructed in order to help identify potential pollutant linkages.
14.2.4 Should a site at any stage of the assessment show it is unlikely to be determined as contaminated land due to the likely absence of a significant contaminant linkage; the council will produce a written statement.
14.2.5 Risk assessments will be undertaken based on Contaminated Land Research 11 ('CLR11') model procedures for the management of land contamination (Environment Agency, 2004).
14.2.6 Where one or more potentially significant contaminant linkages have been identified in the preliminary investigation (desk study and walkover), minimal sampling of the site will be required to see if there is evidence that these exist.
14.2.7 Where results from the preliminary investigation sampling programme reveal elevated concentrations to the extent it is believed by the council that one or more significant contaminant linkages remain on site, then a site investigation sampling strategy will be put together for the purpose of enabling an intrusive site investigation and risk assessment. This work is likely to be contracted out, so the council procedures for tendering and procurement will apply.
14.2.8 Where findings of site investigations show that significant harm or the possibility of significant harm to receptor(s) exists, procedures outlined in Section 11 will be followed. Under such circumstances the council will prepare a risk summary prior to any determination.
14.2.9 Given the complexity of bringing about remediation under Part 2a, it is impossible to predict when the remediation of sites listed on the public register will be complete. The council has a duty to serve Remediation Notice requiring the remediation of statutory contaminated land and it has the power to enforce that notice. The apposite timescales will depend on risk and impacts of the pollutant and the specific impacts of remediation.
14.2.10 All Part 2a duties will be carried out in accordance with the latest guidance issued by DEFRA and the Environment Agency.