8.1 As a major land holder the City Council awards millions of pounds worth of contracts for major new works projects and maintenance works each year. Where such works are taking place on contaminated land or potentially contaminated land the City Council has a duty of care to provide the fullest information possible to contractors including access to any relevant site investigation reports. The contractor will then be in a position to comply with:
- relevant health and safety legislation/guidance, including the Construction Design & Management Regulations (Note: the CDM Regulations place duties on the Council as client as well as the contractor)
- duty of care with respect to carriage of waste and waste disposal.
8.2 Contracts can be awarded by any front line service. It is not acceptable for City Council officers to claim that they were not aware of a problem. Where site specific information is not already available the officer responsible for the contract must ensure that proper enquiries are made to:
- establish the site history using historic maps and the GIS/trades database held within Environmental Health,
- determine if previous site investigation data is available within the City Engineer's Department or Environmental Health & Trading Standards Service,
- where enquiries made under 'a' indicate a potential for contamination but no site investigation data is available then provision must be made to obtain the necessary data before tendering the contract, or make 9 allowance in the specification/bill of quantities for the contractor to undertake the necessary investigation,
- any new data collated under 'c' must be copied to the Environmental Health & Trading Standards Service which will act as the central store for information on site contamination.
8.3 On a number of sites which are owned by the City Council, particularly those which were formerly landfills, site investigation followed by a risk assessment has shown that the site is safe to be used for its current use provided the ground surface is maintained to a high standard. This will normally involve a regular inspection of the surface, regular 'litter' picking to remove fragments of fill which have become exposed, and maintaining the grass cover across the site.
Most of these sites will be under the management of the Leisure Service, but other land holding departments may also be affected. It is essential that it is clear in the maintenance contract that the contractor is responsible for maintaining the vegetation cover across the ground surface, what reporting procedures should take place when the surface is found to be damaged and what additional measures or restrictions are required on a site specific basis. For example, on football pitches goal mouth areas become worn, the City Council may require that such areas be dressed with new clean soil or for all nets and goal posts to be removed on some sites during the summer to give vegetation the chance to establish.
To ensure the site is maintained to an adequate standard, the land holding department must also nominate an officer to undertake a minimum bi-annual inspection to ensure the contractor is maintaining the site to the necessary standard. Note: this will require regular inspection of informal areas of public open space not currently inspected. The staffing and resource implications of this will need to be reviewed by the City Leisure Officer.
8.4 Where the Council or any utility company requires a contractor to place or repair services which cross sites identified as being contaminated the opportunity must be taken to place the service into a clean trench. The old service should be dug out and all arisings removed from site immediately. The arisings should not be placed on the existing ground surface unless underlain by polythene sheeting to avoid the more contaminated material from depth contaminating the ground surface. The new trench should be lined with a geotextile and backfilled with a clean non-porous material such as clay. The cost of these works will be met by the client requiring the work to be undertaken. Where a water service is to be replaced the advice of Portsmouth Water Company and the Environmental Health & Trading Standards Service should be sought. All works must be done in strict accordance with Health and Safety guidance (reference 5).
8.5 Where an easement is requested across land owned by the City Council which is known or suspected to be contaminated, the company requesting the easement must be given full access to information on the site history and any site investigation reports available. The company must only be granted consent for the easement subject to the following restrictions:
- All works must be designed and constructed taking into account the ground conditions and the works must be completed in accordance with a scheme approved by the City Environmental Health and Trading Standards Officer.
- Before commencement of the works a full method statement shall be submitted to and agreed by the City Environmental Health and Trading Standards Officer. All works must be completed in accordance with the agreed method statement.