Corporate Contaminated Land Strategy - 6. Planning Control

For the purposes of the Town and Country Planning Act 1990, the potential for contamination is a material planning consideration, to be taken into account during the normal course of development. The government has indicated that it considers that the redevelopment phase is the most appropriate and cost effective time to deal with contamination issues, stressing that Local Authorities should make full use of the powers available to them in accordance with the guidance issued in Planning Policy Guidance Note 23 (PPG 23). 

Paragraph 4.5 of PPG 23 states "The best way of minimising any associated risks is to ensure that sites which may be contaminated are identified at the earliest stage of planning. The history of the site or nearby sites is the principal factor in determining whether a site is likely to be contaminated or not. The document goes on to say that the responsibility for providing information on whether land is contaminated rests primarily with the developer (Para. 4.10). In districts which contain a significant number of possibly contaminated sites the government suggest that the LPA should add a question on contamination on their standard application form (Annex 10, para. 7)". 

The City Council strategy on Contaminated Land should implement the guidance fully and our development control procedure should be adapted as follows: 

6.1 A question has been added onto the standard Portsmouth City Council planning application form to require developers to provide a brief history of the site indicating all previous known land uses and operations. 

6.2 Where the answer(s) to the new question 13 indicates a potential for contamination, or where the redevelopment will involve the creation of new residential properties, or commercial redevelopment with a site area greater than 250m² a full desk study should be provided by the developer (unless the City Planning Officer in consultation with the CEHTSO determines sufficient information has been provided by the applicant). The desk study will provide a comprehensive site history with historic maps etc. A guidance note is available to assist applicants. (PCC Planning Advice Note 11.) 

6.3 The Planning Officer should liaise with the Environmental Health & Trading Standards Service and wherever the information provided under 6.1 or 6.2 indicates the potential for contamination, or the LA hold such information (which should be copied to the developer). Planning permission shall only be granted subject to conditions requiring appropriate site investigation prior to the commencement of the development, and site remediation prior to occupation of the development, where such is found to be necessary. 

6.4 On sites where the contamination or landfill gas issue is likely to be a physical constraint to the redevelopment options for the site, whether owned by the City Council or an outside body, the Planning Service, Environmental Health & Trading Standards Service, landowner and any other interested parties shall liaise to produce a development brief for the site. This would apply to sites such as the Tipner Redevelopment Area, Paulsgrove Tip and most 7 6.5 former MOD land. 

6.5 Where conditions are imposed on planning approvals the Planning Service must ensure the conditions are complied with before development commences. It is almost impossible to undertake a site investigation or implement remedial measures once development is underway, so all works required by the conditions must be agreed at an early stage. Planning Advice Note 11 which explains issues related to contamination, current guidance documents available, and the timescales necessary for developers to complete site investigation work to comply with planning conditions should be issued to applicants who receive a conditional approval. 

6.6 The LPA is required by the Town and Country Planning Act (GDP - 1995) to consult with the EA in respect of certain types of application. With the recent formation of the Environment Agency, and in view of the increased knowledge regarding gassing landfill sites in the area, the City Planning Officer and the City Environmental Health and Trading Standards Officer pursue an agreement with the relevant officers from the Environment Agency to review what types of application need to be referred to the Environment Agency and for which specific areas of the City. 

6.7 Open discussion of all information related to potential contamination at the development stage and the application of conditions is the only sensible way forward to ensure the safe development of brownfield sites. This openness and validation of the clean up process will ultimately ensure market confidence in the redevelopment of brownfield sites, and thus promote the recycling of brownfield sites which is essential in a City with little/no greenfield sites available. This strategy is also in line with government policy.