Dated: 25th April 2022

Portsmouth City Council (Hampshire Street) (Temporary Prohibition of Driving, Loading and Waiting) (No.84) Order 2022

Notice is hereby given that Portsmouth City Council intends to make the above Order under Section 14(1)(a) of the Road Traffic Regulation Act 1984, as amended by the Road Traffic (Temporary Restrictions) Act 1991.

The Order comes into operation from 9th May 2022 and the effect will be as follows:-

A) TEMPORARY PROHIBITION OF DRIVING, LOADING AND WAITING

HAMPSHIRE STREET
From the junction of Fratton Road to its junction with Hampshire Street Access Road to 1-80 Hale Court Fratton Road.

B) TEMPORARY FOOTWAY CLOSURE

LAKE ROAD
For 40 metres from the junction of Fratton Road.

FRATTON ROAD
For 80 metres from the junction of Lake Road.

C) TEMPORARY SUSPENSION OF BUS LANE RESTRICTIONS

LAKE ROAD
For 40 metres from the junction of Fratton Road.

FRATTON ROAD
For 80 metres from the junction of Lake Road.

D) REASON FOR THE ORDER
To facilitate works to install new Electricity Sub Station.

E) DURATION OF THE ORDER
From 9th May 2022 for 7 weeks or completion of the works, whichever is sooner.

F) DIVERSION
Vehicles diverted from Ernest Road – New Road – Fratton Road – St Marys Road -Shakespeare Road – Ernest Road. No overtaking cyclists signs will be used.
Pedestrian access will be maintained.

Assistant Director of Regeneration (Transport), Portsmouth City Council, Civic Offices, Portsmouth PO1 2NE

A copy of the Order may be requested from networkmanagement@portsmouthcc.gov.uk or at the reception desk in the Civic Offices.