Dated: 27th September 2021
Portsmouth City Council (Locksway Road) (Temporary Prohibition of Loading and Waiting) (No.111) Order 2021
Notice is hereby given that Portsmouth City Council intends to make the above Order under Section 14(1)(a) of the Road Traffic Regulation Act 1984, as amended by the Road Traffic (Temporary Restrictions) Act 1991.
The Order comes into operation from 11th October 2021 and the effect will be as follows:-
A) TEMPORARY PROHIBITION OF LOADING AND WAITING
LOCKSWAY ROAD
Outside Nos. 103 – 114.
B) REASON FOR THE ORDER
To facilitate SGN gas works.
C) DURATION OF THE ORDER
From 11th October 2021 for 12 days or completion of the works, whichever is sooner.
D) DIVERSION
No vehicle diversion. Bus stop will be closed and relocated.
Pedestrian access will be maintained.
Pam Turton, Assistant Director of Regeneration (Transport), Portsmouth City Council, Civic Offices, Portsmouth PO1 2NE
A copy of the Order may be requested from networkmanagement@portsmouthcc.gov.uk