And that’s a wrap! Our contractors have pretty much finished on site and we’ve handed the keys over to the new Hilsea Lido team. The pool had to sit for a while with no filtration and no chlorine as part of the pool test. The filters are now switched on, and the chlorine has been added, and there’s a little vacuum in there giving it a good clean. The landscaping is all complete, with resin all around and new turf laid. The new team will now spend time adding the finishing touches, including a pool cover, painting the old building, the sauna, lights, bunting, and lots more.
Description of pictures (first to last):
Work is progressing at a rate of knots now the tent is fully dismantled. The pool is full and being tested for a week before chemicals are added and the filters are switched on. The changing rooms are being installed and will soon look like little beach huts. The outdoor shower bases have been painted, and the showers are being plumbed in. Resin is being the site, as well as depth markers. Handrails and ladders have been fitted around the pool.
Description of pictures (first to last):
The tent has started being dismantled. It take approximately two weeks to remove the whole structure. Once it’s gone, work can continue in the pool with fixing the handrails and ladders in place. An entrance kiosk has been put into place, with the same design as the toilet and shower units.
Description of pictures (first to last):
Anti-slip paint has been added to the shallow ends of the pool and the lagoons. A pendulum test will be carried out to measure the thickness of the anti-slip. Tarmac has been laid around one of the outdoor shower bases, in preparation for the final finished surface. The loading area up by the chemical store is finished. Ground work to level the entrance to the site has began, with dirt being removed and hardcore ready to lay.
Description of pictures (first to last):
The painters have done a fabulous job painting the black racing stripes in the pool. There are stripes width ways as well to mark where the 1.35m line is. There are four width ways gaps across the pool, which are intentional and will be filled with expansion filler. This is to protect the pool against natural movement. The electric substation is also fully installed by the Blue Lagoon.
Description of photos (first to last):
The pool floor is mostly painted, with some gaps left for remedial work. Soon, the tent will be removed carefully, but just in case the tiles have been carefully covered with timber to protect them. Once the tent is removed, the handrails and ladders will be installed around the pool.
Description of photos (first to last):
The painting has begun on the pool floor now. The base coat needs to be applied first, and the blue paint must be applied within four days or it won’t adhere properly, so the painters are working in stages. The wiring for the lights is being put in place, with future maintenance in mind.
Description of photos (first to last):
The transformation from grey has started. The pool has had a large amount of undercoat applied to the walls and they are starting on the topcoat. The base paint needs to have the top coat applied within four days to fit with the manufacturer’s guidelines, which is why they’re doing it in stages.
Description of photos (first to last):
It’s all progressing nicely with SSE starting their work to bring power to Hilsea Lido. The team have made holes in the tiles ready for handrail installation. They’ve started fitting the pool lights, but these won’t be properly fitted for a while yet. New gates have been installed so deliveries can drop chemicals to the store without needing to cross the site, this is much safer.
Description of photos (first to last):
Since announcing the team behind Sea Lanes Brighton as our operator, we’ve made some changes to the final part of the construction programme to accommodate some of their ideas. Doing this now will mean we do these more quickly, efficiently and cost-effectively in the long run. We are now operating to the new schedule and the build should be complete before the year is up.
Description of photos (first to last):
The entrance of the lido is having a bit of an overhaul. The old concrete is being dug up ready to surface it properly. The chemical store is built and ready to be rendered. The doors are securely fitted. Bollards are being installed around the plant room to keep the area safe. The plant room is having lots of pipes connected to each other, to keep the pool water sparkling clean.
Description of pictures (first to last):
Rendering is continuing across the floor, and tiling is continuing. At this point, there’s been approximately 2,700 tiles laid! The team are working flat out to make the 67m pool perfect. Outside, soil has been laid ready for the grass, and soon the resin flooring will be laid.
Description of pictures (first to last):
Inside the tent, the tiles have started being laid around the edges of the pool. There will be tiles either side of the gulley, finger rests, and tiles below that. The team have been busy rendering the walls and have now started on the floor, they’ve deliberately left a gap around the edges to the tilers can continue working. Groundwork is still happening around the outside, with the haul road being removed, and concrete bases for outdoor showers installed.
Description of pictures (first to last):
The temporary ten structure over the tent has been built, protecting the pool from the weather to allow the final touches. Inside the tent the pool walls are being rendered and the top edges are being screeded so the tiles have a nice smooth surface to stick to. In the plant room, filtration equipment is being fitted by experts Barr and Wray. The new chemical store has been built and will be properly fitted with essential safety equipment. The shower bases on the west side of the site are being laid as well as other groundworks including excavation and manhole adjustments.
Description of pictures (first to last)
The scaffolding for the temporary tent structure is finished and they have started covering it – this is to protect the pool from the weather while finishing touches are complete. There’s lots of groundwork being done around the site including installing electric cables and drainage. The base has been built for the chemical store, and the team have started installing outdoor showers.
Description of pictures (first to last):
The team have started to build the large tent that will cover the 67m pool. This will be a temporary cover to protect the pool from the weather while the finishing touches are made to the pool. Rendering has been applied to the walls to smooth it down ready to be painted. The plant room now has a roof (hooray) with new lighting installed. The filtration tanks will have ballast and sand added to them, where any dirt and debris will be trapped, keeping the pool water clear.
Description of pictures (first to last):
The filtration tanks have now been installed and the roof can be fitted on the plant room. The team are preparing the pool for the next stages by taking off the smooth area of the concrete, this will ensure the render sticks to the rougher surface. There’s a sample panel onsite to give an idea of what the final pool will look like. A large scaffold tent will be erected over the pool, and to weigh it down there will be 160, one-tonne water tanks put in place.
Description of pictures (first to last):
Work is still being carried out on the plant room. The team are pouring concrete on the floor to create a raised section for the filtration equipment, as well as other boxes for other raised areas. There is space left at the top of the walls to rest the steel joists in.
Description of pictures (first to last):
The pool has passed its testing stage and there will be a thorough update coming soon.
The steel roof bars from the plant room have now been removed. New ones will be fitted soon when the walls have been concreted. The three blue filtration tanks will soon be craned into the plant room. And soon a new chemical store will be built next to the plant room and a double gate installed along the fence, to make deliveries safer and easier.
Description of pictures (first to last):
The pool is still being tested, and we’ll have more information on this soon.
In the plant room, the shuttering has been installed and the walls will be made taller than they are now. The concrete pour has started on the walls. The ground around the modular shower units has been brought up to level (no steps to contend with so they’ll be fully accessible) and there will be a Changing Places toilet and shower room installed. Blockwork is being laid to create flower beds ready for planting.
Description of pictures (first to last):
The pool is undergoing testing at the moment – but we’ll have more of an update on this for you next time.
In the plant room, the designs for the shuttering are being finalised, and soon the walls will be ready for the concrete pour. Once the room is stable, the steel bars across the top will be removed. The ground around the edge of the pool is ready for surfacing, as soon a large tent will be erected over the pool to protect it from the elements while they move on to the next stage. The floor needs to be completely solid to support the structure.
Description of pictures (first to last):
We’ve been having some tricky weather lately, but the team are progressing well. They’re doing work in the plant room where they’ve poured concrete on the base and are now adding steel bars around the edges of the room. Once this is done, they’ll add more concrete to the walls, making it structurally sound before they remove the red bars across the top.
They’ve laid the hard standings for the beach huts (which will act as changing rooms) and they’ve also been preparing the ground ready for tarmac, and then resin will be the final finish.
Description of pictures (first to last):
You may have noticed the bright cabins that have been installed at the lido – these are modular shower units, they just need to be plumbed in and have gas and electric connections.
The pool is completely concreted, and now work will focus on the surrounding ground and in the plant room. We’re currently pumping the rain water out of the pool that collected in there over the festive break.
The plant room floor has been concreted, and work will start to reinforce the walls. The three filtration tanks you can see on the site will be installed in the plant room once its ready.
Description of pictures (first to last):
We’re almost done with the concrete work, just the ends of the pool and balance tank walls left to go! By next week, concreting will be a thing of the past (well, almost). The team have created an area on the north of the site, which is where the modular shower units will go which are arriving next week! And on the south side they’re busy preparing the ground for 20 beach huts, which will be the changing rooms. We are having some trouble in the plant room – the original seawater pipes from 1935 are capped, but the immense pressure of water when the tide is in still forces water through and into the plant room. The team has a plan to resolve this in the new year by raising the floor level and encasing the pipes.
Description of pictures (from first to last):
The walls are taking shape with concrete being poured in different sections. The team are having to battle with the weather, using frost covers on freshly poured concrete – if water droplets get in, they’ll freeze and when they thaw it’ll create air bubbles. Work has started on the ground to install concrete slabs for Portakabins (temporary portable buildings), which will be the toilet and shower blocks.
Description of pictures (from first to last):
The south wall is nearly complete, with only a small section left before the final concrete pour. The lagoon, designed with a beach-style entry for accessible access, is set for its final concrete pour next week, which will mean the entire pool base is concreted! The filtration pipes emerging from the back of the wall highlights some of the careful planning the team has to tackle when concreting the walls.
Description of pictures (from first to last):
The steel reinforcement is now in place along the restored ‘lagoons’ in the north side of the pool, ready for the concrete pour in the next couple of weeks. The first sections of the pool wall have now been formed and the shuttering removed. The surface is currently being prepared by jet washing the concrete. This exposes the aggregate and will ensure that the rendered finish can stick (or ‘key’) to the concrete wall.
Description of pictures (from first to last):
Our Hilsea Lido contractors have been very busy onsite despite the awful weather we’ve had. The last of the concrete has been poured onto the base of the pool, bringing it up to its final level and is now ready for rendering. Now they’re preparing the sides with steel work and they will soon be concreted. They’re still beavering away securing all the underground pipework as part of the filtration system.
Description of pictures (from first to last):
The team have concreted the base and have now moved on to the slopes either side to install the steel reinforcing, which will then have concrete poured over the top, like the centre section. Once complete, there will be 30 lorry loads of concrete used in the construction of the pool!
Description of pictures (from first to last):
The team have been busy on site this week again. With the pool they’ve been preparing the base for the last concrete pour next week. This will bring the base of the pool up to the final level. They’ve been digging trenches around the edge of the pool ready to install the pipe work, and while doing so they’ve uncovered the foundations for the old diving board. The backwash tank has now been installed and concreted into place.
Description of pictures (from first to last):
This week a 10.5m backwash tank has been delivered. This is a type of water filter that can hold over 50,000 litres of water! The team dug a huge hole ready for the tank to be fitted underground next week. You can see how much mud and clay has been removed from the ground – this sparked conversation about the risks of digging up bombs from the war. Before any work was done an extensive ‘unexploded ordnance survey’ was completed, to ensure the safety of the site. The team have also been busy fitting pipes into the pool itself.
Description of pictures (from first to last):
This week, the team have installed the first level of starter bars (221 to be exact). This steel work will help secure the old concrete to the new concrete, making the whole structure as secure as possible. Concrete ‘blinding’ has been carried out in the shallower parts of the pool – this makes the foundations smooth, level and stable so further work can be carried out. A sample panel has been delivered – there will be lots of these panels around the edge of the pool, and the finishing material will be installed on the top of them, as well as 32 lights within the pool itself.
Description of pictures (from first to last):
The team have continued to pour concrete into the bottom of the pool, with another 750mm to go. Once finished, the pool will be 2.6m deep at the lowest point. By carrying out this work, we’ll make sure the pool lasts for another century, by reinforcing it and adding weight to the base. This will counteract the water table pushing the pool upwards, which is damaging the structure.
We’ve mentioned in the past about the new ledge being created around the pool. It has now been formed around the southern edge. This means you’ll be able to sit on the edge of the pool and safely dangle your feet in, or perch on the ledge itself.
Descriptions of pictures (from first to last):
To ensure the pool lasts for another century, we’re adding weight to its base. This is important because the groundwater is pushing the pool upwards, which can damage its structure. The extra concrete in the middle will help counteract this pressure.
Descriptions of pictures (from first to last):
The team have emptied the plant room and the pool and are starting to chip away at the edges of the pool to make a foot rest around the edge. The pool keeps filling up with water from underground, so the team are having to pump this out daily.
Descriptions of pictures (from first to last):
The team have been busy removing the filtration equipment and pipework from the plant room.
Descriptions of pictures (from first to last):
The team have started making the plant room safe by removing the roof and the filtration equipment.
Descriptions of pictures (from first to last):
The spectator stand at the north of the site was found to be unsafe and so had to be removed.
Descriptions of pictures (from first to last):