And that’s a wrap! Our contractors have pretty much finished on site and we’ve handed the keys over to the new Hilsea Lido team. The pool had to sit for a while with no filtration and no chlorine as part of the pool test. The filters are now switched on, and the chlorine has been added, and there’s a little vacuum in there giving it a good clean. The landscaping is all complete, with resin all around and new turf laid. The new team will now spend time adding the finishing touches, including a pool cover, painting the old building, the sauna, lights, bunting, and lots more.
Description of pictures (first to last):
- The completed pool is being cleaned, filtration now on and chlorine now in
- The changing rooms are complete
- Turnstiles have been added to the entrance
- Turf has been laid in front of the shower blocks